Transportation

Tennessee to Develop Strategy to Improve Transportation and Land Use Planning

NGA Center Selects Tennessee to Participate in 10-Month Initiative
 
NASHVILLE – Tennessee has been selected by the National Governors Association Center for Best Practices (NGA Center) to participate in the Policy Academy on Shaping a New Approach to Transportation and Land Use Planning. The state will develop a Corridor Management Agreement in one of the state’s urban areas that will later be applied to other transportation corridors across the state. The goal is to create a system that helps local planning agencies learn how to make land use decisions that better coordinate with transportation decisions made at the local and state level. Colorado, Maryland, Washington and West Virginia have also been selected to participate in the program.

TDOT Vehicles in Knoxville Running on Cleaner E85 Fuel

New E-85 Pumps Now Available at TDOT Region One Complex
 
KNOXVILLE, Tenn. – In an effort to conserve resources and to improve air quality, the Tennessee Department of Transportation is celebrating a conservation milestone. As of this week, fueling stations at TDOT’s Region One Complex Office now offer E85 fuel for state vehicles. E85 is a blend of ethanol and gasoline that burns cleaner than regular gasoline thus reducing a number of airborne pollutants.

TDOT to Release Details on U.S. 64 Rockslide Clean-up

CHATTANOOGA, Tenn. – Tennessee Department of Transportation Commissioner Gerald Nicely will visit the U.S. 64 rockslide sites in Polk County on Friday, March 19. Nicely will update the progress made on clearing the slides and improving the roadway and the schedule for reopening U.S. 64.  

I-440 Interchange Ramps to Close This Weekend for Concrete Repairs

Contract crews replace damaged concrete along I-440 in Nashville. The rehabilitation project is being funded through the American Recovery & Reinvestment Act.
Contract crews replace damaged concrete along I-440 in Nashville. The rehabilitation project is being funded through the American Recovery & Reinvestment Act.
NASHVILLE – Tennessee Department of Transportation crews will close two interchange ramps on Interstate 440 in Nashville this weekend as a major concrete repair project continues. The closures are as follows:
 
*      Ramp from I-440 West to Interstate 65 South
*       Ramp from Interstate 65 North to I-440 West
 
The ramps will close beginning at 4:00 a.m. Saturday, March 20, 2010 and will reopen no later than 6:00 a.m. Monday, March 22, 2010.

Polk County US-64 Rockslide Update for March 17

Workers continue to remove break up rock and haul debris from the boat ramp located at the foot of TVA Ocoee 2 Dam and along the roadway.
Workers continue to remove break up rock and haul debris from the boat ramp located at the foot of TVA Ocoee 2 Dam and along the roadway.
CHATTANOOGA, Tenn. – Work continues to progress on the stabilization and clearing of the rockslide along U.S. 64 at Mile Marker 17 in Polk County with around the clock work set to begin Tuesday. Construction crews continued scaling loose rock and debris from the eastern side of the slope with machinery today as heavy equipment worked along the roadway and river bank breaking up large rock and hauling away debris from the site.  Rock bolting crews worked through the evening and early morning hours drilling 15 ft., 25 ft. and 40 ft. deep holes along the upper and middle sections of the central part of the slope in order to grout and install rock bolts.  Daytime and night time crews will continue working a 24/7 schedule, weather permitting, until the slide remediation and cleanup is completed.
 

Evaluations continue for rockslide on U.S. 129/SR-115

 
KNOXVILLE, Tenn.- Both lanes on U.S. 129/SR-115 remain closed at the scene of a rockslide approximately two miles south of the Chilhowee Dam and more than 13 miles north of the  Tennessee and North Carolina state line.
 
TDOT geotechnical engineers have conducted preliminary evaluations of the slide and are currently developing a plan to stabilize the mountainside and re-open the road safely and expeditiously.   No timeline has been confirmed.
 
Meanwhile, motorists can take temporary detours around the rockslide area.
 

Polk County US-64 Rockslide Update for March 15

TDOT Chief Engineer Paul Degges (rt.) and other TDOT personnel receive updates on the rockslide removal project from representatives with contractor Charles Blalock & Sons
TDOT Chief Engineer Paul Degges (rt.) and other TDOT personnel receive updates on the rockslide removal project from representatives with contractor Charles Blalock & Sons
Close up view of rock bolts grouted into position on the slope
Close up view of rock bolts grouted into position on the slope
Blasting on the eastern slope
Blasting on the eastern slope

Debris Removal and Rock Bolting Operations Continue

CHATTANOOGA, Tenn. – Over the weekend, daytime construction crews continued hauling slide debris from the site and reconstructed the 275 ton crawler crane approximately 30’ to the east so that hand and mechanical scaling could continue on the eastern face of the slope.  The contractor resumed scaling today and will continue until the slope is free of loose rock and debris that might otherwise serve as a hazard to workers and future traffic on the roadway surface below.
 

Polk County US-64 Rockslide Update for March 12

Midnight at the rockslide
Midnight at the rockslide
Work on put-in ramp
Work on put-in ramp
24 Hour Schedule Continues
 
CHATTANOOGA, Tenn. – Crews continued working a 24 hour schedule with hand and mechanical scaling, drilling, and blasting proceeding on the eastern side of the main slide area and along the river bank during daylight hours and rock bolting operations taking place on the western slope during night time hours.  This schedule is expected to continue through the weekend and into next week as weather permits.  Night time rock bolting operations are expected to shift to a 24 hour, 7 day a week schedule as soon as the slope blasting and scaling operations are completed.
 

U.S. 25/70 in Cocke County to Close for Bridge Inspection

TDOT to Detour Traffic During Inspection
 
Knoxville, Tenn. – Motorists using U.S. 25/70 (State Route 9) will need to take an alternate route Wednesday, March 17 when TDOT bridge inspectors close the bridge over the French Broad River in Newport to perform a routine bridge inspection.
 
U.S. 25/70 (State Route 9 or East Broadway) in Newport will be closed from 9:00 a.m. until 3:00 p.m. on March 17. Motorists will be detoured onto U.S. 321 and State Route 340.
 

All lanes temporarily opened on The Spur

Mold used to make concrete panels for rock facade
Mold used to make concrete panels for rock facade
Concrete panels to be used to make rock facade
Concrete panels to be used to make rock facade
Knoxville, Tenn. –  Behind the scenes work has allowed the Tennessee Department of Transportation to temporarily open all lanes of U.S. 441 (The Spur) in Sevier County.
 
Emergency contractor Charles Blalock and Sons, Inc. is currently working offsite utilizing molds to pour concrete panels that will form a stained rock façade which will cover the recently constructed retaining wall. The retaining wall was built during phase one of the project to stabilize the rock slope above the roadway.
 
TDOT estimates crews will begin to install the rock façade during the week of March 15. At that time one southbound lane will close to allow crews to safely work on phase two of the rockslide repairs.
Syndicate content Get RSS News Feed